Time And Work MCQ Set 7

เคนเคฐ Government Jobs เค•เฅ€ update เค•เฅ‡ เคฒเคฟเค เคœเฅเคกเคผเฅ‡เค‚

image_printDownload this pdf

TIME AND WORK MCQ SET 7

1. A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days . If A is twice as good a workman as C , then in what time will B alone do 40% of the same work ?

(a) 12 days

(b) 10 days

(c) 18 days

(d) 15 days

Show Answer

Answer: A

2. To do a certain work , A is 40% more efficient than B . Working together , then can do the same work in 15 days . A started the work and left after 15 days . B and C together completed the remaining work in next 10 days . C alone can do one third of the original work in :

(a) 36 days

(b) 21 days

(c) 30 days

(d) 24 days

Show Answer

Answer: D

3. A can complete 25% of a work in 15 days . He works for 15 days and then B alone finishes the remaining work in 30 days . In how many days will A and B working together finish 50% of the same work?

(a) 24

(b) 20

(c) 12

(d) 25

Show Answer

Answer: C

4. P can do one-fourth piece of some work in 18 days . She completed 37.5% of that work and left it . Q completed the remaining work in 40 days . Working together they will complete 17/48 part of the same work in :

(a) 10 days

(b) 8 days

(c) 12 days

(d) 6 days

Show Answer

Answer: C

5. P can finish a work in 18 days . When he had worked for 5 days , Q joined him . If both of them together completed the remaining work in 13/5 days , then in how many days can Q alone finish 2/3 of the same work?

(a) 5

(b) 4

(c) 2

(d) 3

Show Answer

Answer: D

6. A alone can do 2/5 of a work in 12 days . B is 25 percent more efficient than A . C alone can do the same work in 12 days less than B . D is 25 percent less efficient than C . If they all work together , then the work will be completed in how many days?

(a) 240/53

(b) 180/43

(c) 300/47

(d) 200/57

Show Answer

Answer: A

7. A and B can do a certain work in 18 days and 30 days , respectively . They work together for 5 days . C alone completes the remaining work in 15 days . A and C together can complete 5/6th part of the same work in:

(a) 6 days

(b) 8 days

(c) 9 days

(d) 5 days

Show Answer

ย Answer: C

8. A can complete a work in 60 days . B is 25% more efficient than A . They work together for 15 days . C alone completes the remaining work in 14 days . B and C together will complete 5/8th part of the original work in :

(a) 18 days

(b) 16 days

(c) 12 days

(d) 15 days

Show Answer

Answer: C

9. X and Y complete a certain work in 16 days and 24 days , respectively . They work together for 4 days . Z alone completes the remaining work in 10 1/2 days . Y and Z together can complete 7/8th part of the same work in :

(a) 10 days

(b) 12 days

(c) 8 days

(d) 9 days

Show Answer

Answer: D

10. A and B can do a certain work in 12 and 18 days , respectively . They work together for 5 days . The remaining work was completed by C alone in 27 1/2 days . What part of the same work can be completes by A , B and C together in 6 days?

(a) 9/10

(b) 29/30

(c) 14/15

(d) 5/6

Show Answer

Answer: A


Share this post and help your Friends

Leave a Reply

Your email address will not be published. Required fields are marked *

Disclaimer: Any information regarding examination forms, results/scores, answer keys published on this website is provided for the immediate information of the examinees only and should not be considered as a legal document. While the Gear Institute team has made every effort to ensure the accuracy of the information provided including the official links, we are not responsible for any inadvertent error that may appear in the examination results/grades, answer keys or admission schedule/dates. Also, we accept no liability for any loss or damage caused by any deficiency, defect or inaccuracy in the information available on this website. Please contact us through the Contact Us page if you require any correction.

Note: Gear Institute is not a Consultant and will never charge any candidates for Jobs. Please be aware of fraudulent calls or emails.


Top